Latest Updates


Thursday 26 October

Temporary side track constructed and a 25t rated temporary bridge has now been installed. Traffic will now be diverted through the temporary bridge and the existing bridge demolished. 

Pilling pads have been completed and the contractor has commenced pilling work. Precast girders have now been casted, expected for site delivery soon.

IMG_4439 IMG_E4459

IMG_4463 IMG_4543


Tuesday 22 August

Temporary side track is being constructed and the temporary bridge has now been installed.

Contractors will undertake the demolition of the existing bridge structure on Monday 28 August, upon completion of the temporary side track.

IMG-4102 IMG-4107


Wednesday 9 August

Installation of the temporary bridge has now commenced.

Boorolong U1 Boorolong U2    Boorolong U3


Tuesday 1 August 2023

Installation of a temporary bridge across Boorolong Creek Bridge will be commenced on 8 August 2023. This will allow for an ease of access enabling the construction phase of this project to commence.