Thursday 26 October
Temporary side track constructed and a 25t rated temporary bridge has now been installed. Traffic will now be diverted through the temporary bridge and the existing bridge demolished.
Pilling pads have been completed and the contractor has commenced pilling work. Precast girders have now been casted, expected for site delivery soon.
Tuesday 22 August
Temporary side track is being constructed and the temporary bridge has now been installed.
Contractors will undertake the demolition of the existing bridge structure on Monday 28 August, upon completion of the temporary side track.
Wednesday 9 August
Installation of the temporary bridge has now commenced.
Tuesday 1 August 2023
Installation of a temporary bridge across Boorolong Creek Bridge will be commenced on 8 August 2023. This will allow for an ease of access enabling the construction phase of this project to commence.