Burns Rd Resheet

3.9km resheet of Burns Rd

This work will be upgrading the roadside drainage system. Initial works will involve the installation of up to 5 new pipe culverts leading on and up to applying a 100mm gravel overlay along the whole extent of the road. This work is expected to take up approx 6wks.

Status:

  • 5 new storm water pipes have been installed.
  • Gravel resheeting work has commenced, and will take approximately 2 weeks depending on the weather to complete.

Motorists are asked to comply with signage, drive to the conditions and watch out for workers and plant in the road.