Moredun Dams Rd resheet

The Moredun Dams resheet comprises of a new gravel overlay along a 5.5km segment of the road, rehabilitation of existing drainage infrastructure and installation of new pipes. Works have commenced and subject to weather it's hoped that this $217,140.00 investment in our rural road network will be complete early in the New Year. Road users are asked to be mindful of conditions, roadside signage and to follow instruction from Council staff.

Status:

  • Gravel resheet has been completed as of 8 January 2018
  • Finalising of drainage works to be completed by 12 January, weather permitting